The relationship between men, work, and time can be written as: \[ \text{Men} \times \text{Work} \propto \text{Time} \] Assuming all other factors remain the same.
| Men | Tunnel Length | Days | |
|---|---|---|---|
| Initial | 140 | 1.5 km | 60 |
| Remaining | X | 4.5 km | 140 |
We use the direct proportion formula: \[ X = 140 \times \frac{4.5}{1.5} \times \frac{60}{140} \]
Simplifying: \[ X = 140 \times 3 \times \frac{60}{140} = 3 \times 60 = 180 \]
Hence, the number of men required = \( \boxed{180} \)
Additional men needed: \[ 180 - 140 = \boxed{40} \]
40 additional men are required to complete the remaining 4.5 km tunnel in 140 days.
A contractor agreed to complete a road project in 200 days with 140 workers.
However, after 60 days, only \( \frac{1}{4} \) of the total road was completed.
The amount of work left: \[ 1 - \frac{1}{4} = \frac{3}{4} \]
Remaining time to complete the work: \[ 200 - 140 = 60 \text{ days} \]
Let \( x \) be the number of extra persons needed to complete the remaining \( \frac{3}{4} \) of the work in 60 days.
We use the work formula: \[ \frac{M_1 \times D_1}{W_1} = \frac{M_2 \times D_2}{W_2} \] where \( M \) = men, \( D \) = days, \( W \) = work
Substituting values: \[ \frac{140 \times 60}{\frac{1}{4}} = \frac{(140 + x) \times 60}{\frac{3}{4}} \]
Simplify both sides: \[ 4 \times 60 = \frac{(140 + x) \times 4}{3} \]
Multiply both sides by 3: \[ 240 \times 3 = (140 + x) \times 4 \Rightarrow 720 = 4(140 + x) \]
Solve for \( x \): \[ 140 + x = 180 \Rightarrow x = 180 - 140 = \boxed{40} \]
40 additional workers are needed to complete the remaining road on time.