Question:

A can do a work in 20 days and B can do it in 10 days. A starts the work and works alone for 5 days. Then B joins A and they finish the work. In how many days total does the work get finished?

Show Hint

Calculate individual work rates, then sum them for combined work rate.
Use remaining work and combined rate to find remaining time.
Updated On: Jun 9, 2025
  • 10
  • 12
  • 9
  • 8
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

Step 1: Find daily work rate of A and B
- A can complete work in 20 days, so A's work rate = $\frac{1}{20}$ work/day
- B can complete work in 10 days, so B's work rate = $\frac{1}{10}$ work/day
Step 2: Work done by A alone in 5 days
Work done by A in 5 days = $5 \times \frac{1}{20} = \frac{5}{20} = \frac{1}{4}$
Step 3: Remaining work
Remaining work = $1 - \frac{1}{4} = \frac{3}{4}$
Step 4: Combined daily work rate of A and B
Combined rate = $\frac{1}{20} + \frac{1}{10} = \frac{1}{20} + \frac{2}{20} = \frac{3}{20}$ work/day
Step 5: Time taken by A and B together to complete remaining work
Time = $\frac{\text{Work}}{\text{Rate}} = \frac{3/4}{3/20} = \frac{3}{4} \times \frac{20}{3} = 5$ days
Step 6: Total time
Total time = 5 days (A alone) + 5 days (A and B together) = 10 days
Hence, the work is completed in 10 days.
Was this answer helpful?
0
0