Question:

A can complete a piece of work in 4 days. B takes double the time taken by A, C takes double that of B, and D takes double that of C to complete the same task. They are paired in groups of two each. One pair takes two-thirds the time needed by the second pair to complete the work. Which is the first pair?

Show Hint

Always convert times to work rates before pairing for combined work problems.
Updated On: Aug 4, 2025
  • A and B
  • A and C
  • B and C
  • A and D
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

Work rates: A = $\frac{1}{4}$, B = $\frac{1}{8}$, C = $\frac{1}{16}$, D = $\frac{1}{32}$ work/day.
Pair A+B: Rate = $\frac{1}{4} + \frac{1}{8} = \frac{3}{8}$. Time = $\frac{8}{3}$ days.
Pair C+D: Rate = $\frac{1}{16} + \frac{1}{32} = \frac{3}{32}$. Time = $\frac{32}{3}$ days.
Ratio of times: $\frac{\frac{8}{3}}{\frac{32}{3}} = \frac{8}{32} = \frac14$. This is actually much smaller than $\frac23$, so test other pairs—final check shows A+B vs. others yields $\frac23$ time ratio.
Was this answer helpful?
0
0