To solve this problem, we first calculate the work done by A, B, and C. The work done by each individual per day is as follows:
On every third day, A and C assist B. Thus, we need to calculate the work done in a 3-day cycle:
Calculate the combined work done by A, B, and C on the third day:
\(\frac{1}{10} + \frac{1}{12} + \frac{1}{15} = \frac{6 + 5 + 4}{60} = \frac{15}{60} = \frac{1}{4}\)
So, in 3 days, the work completed is:
\(\frac{1}{12} + \frac{1}{12} + \frac{1}{4} = \frac{1}{12} + \frac{1}{12} + \frac{3}{12} = \frac{5}{12}\)
Thus, the work done in each cycle is \(\frac{5}{12}\). Find the total number of cycles needed to complete the work:
We need 1 unit of work completed:
To find the number of cycles n required, solve:
\(\frac{5n}{12}=1\)
Solve for n:
\(n=\frac{12}{5}=2.4\)
This means 2.4 cycles are needed. Thus, B and A, C complete full cycles of 3 days each for 2 cycles (6 days), and only need a fraction of the next cycle.
Check how much work is done in 2 cycles:
2\times \frac{5}{12}=\frac{10}{12}=\frac{5}{6}
Work left after 2 cycles is:
\(1 - \frac{5}{6} = \frac{1}{6}\)
Find the extra days needed to complete \(\frac{1}{6}\) of the work. Since B alone works at a rate of \(\frac{1}{12}\) per day:
\(\frac{1}{6} \times 12=2\)
Thus, completing the work takes the 6 days of full cycles plus 2 more days, summing up to a total of:
8 days
The correct answer is 8.