Step 1: Determine the total work.
The total work can be calculated in terms of 'men-days'. We know that 24 men can complete the work in 16 days. Therefore, the total work is:
\[
\text{Total Work} = 24 \times 16 = 384 \text{ men-days.}
\]
Step 2: Calculate the rate of work.
The rate of work for 1 man per day is:
\[
\text{Rate of 1 man} = \frac{1}{384} \text{ work per day.}
\]
Similarly, the rate of work for 1 woman per day is:
\[
\text{Rate of 1 woman} = \frac{1}{192} \text{ work per day.} \quad (\text{since 16 women complete the work in 12 days})
\]
Step 3: Work done in the first 6 days.
In the first 6 days, 8 men and 8 women worked. The rate of work per day by 8 men and 8 women is:
\[
8 \times \frac{1}{384} + 8 \times \frac{1}{192} = \frac{8}{384} + \frac{8}{192} = \frac{1}{48} + \frac{1}{24} = \frac{3}{48} = \frac{1}{16} \text{ work per day.}
\]
Thus, in 6 days, the work done is:
\[
6 \times \frac{1}{16} = \frac{6}{16} = \frac{3}{8}.
\]
Step 4: Remaining work and the new group.
The remaining work is:
\[
1 - \frac{3}{8} = \frac{5}{8}.
\]
The remaining work should be completed in 4 more days. Hence, the work done in one day by the new group (after adding \( x \) men) is:
\[
\frac{5}{8} \div 4 = \frac{5}{32}.
\]
The work rate of the new group is:
\[
8 \times \frac{1}{384} + 8 \times \frac{1}{192} + x \times \frac{1}{384} = \frac{1}{48} + \frac{1}{24} + \frac{x}{384} = \frac{5}{32}.
\]
Simplifying:
\[
\frac{1}{48} + \frac{1}{24} = \frac{1}{16},
\]
\[
\frac{1}{16} + \frac{x}{384} = \frac{5}{32},
\]
\[
\frac{x}{384} = \frac{5}{32} - \frac{1}{16} = \frac{5}{32} - \frac{2}{32} = \frac{3}{32},
\]
\[
x = 36.
\]
Step 5: Conclusion.
The value of \( x \) is 36.