Question:

Which among the following is NOT a scheduling strategy for television programming?

Updated On: May 21, 2025
  • Bridging
  • Cold Switching
  • Hammocking
  • Stripping
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

The correct option is(B): Cold Switching