Question:

Unliquidated damages means

Show Hint

Unliquidated damages are not fixed by a contract and must be determined by the court based on the specifics of the case.
Updated On: June 02, 2025
  • Damages to something solid
  • Damages caused by a firm which has gone in liquidation
  • Damages to a firm in the hands of receivers
  • Damage to be assessed by a court as these are not pre-determined
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

Unliquidated damages are those that are to be assessed by a court, as they are not predetermined and depend on the situation and the court's discretion.
Was this answer helpful?
0
0

AP LAWCET Notification