Question:

Three men and eight machines can finish a job in half the time taken by three machines and eight men to finish the same job. If two machines can finish the job in 13 days, then how many men can finish the job in 13 days?

Updated On: Aug 21, 2024
  • 10
  • 12
  • 13
  • 14
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

Assuming one machine completes 1 unit of work per day
Given that combined effort of two machines allows them to finish the job in 13 days.
Therefore, work = 2×1×13 = 26 units.
Let the daily work output of one man be denoted by 'm.'
From the given equation 3m + 8 × 1 = 2(8m + 3 × 1), we find that m = 2/13 units.
If 'x' represents the number of men required to complete the work in 13 days,
the equation xm × 13 = 26 units
This leads to the conclusion that x is equal to 13 men.
Was this answer helpful?
0
0

Top Questions on Time and Work

View More Questions