There is a critical activity is going to have a cost of Rs. 30,000. If this activity is getting completed in 15 days and this work will done in 12 days there will be a cost of Rs. 54,000? Statement I: This crashing is advisable economical if indirect cost is Rs. 8,500 per day. Statement II: This crashing is advisable economical if indirect cost is Rs. 10,000 per day.

Updated On: Jul 1, 2024
  • Statement I & II both are correct
  • Statement I & II both are incorrect
  • Statement I is correct & Statement II is incorrect
  • Statement I is incorrect & Statement II is correct
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

The correct option is (C): Statement I is correct & Statement II is incorrect