Question:

The time wasted by the operator due to breakdown, non-availability or supply of tool and material is:

Show Hint

To optimize production, reduce down time by ensuring timely maintenance and a steady supply of tools and materials, preventing unnecessary delays.
Updated On: Feb 27, 2025
  • Down time
  • Setup time
  • Unit operation time
  • Allowance
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

Down time refers to the period during which the operator cannot perform productive work due to various factors such as equipment breakdowns, non-availability of tools, or shortage of materials. This time is considered unproductive and contributes to inefficiencies in the production process. Setup time involves the preparation of machines or tools before starting a production run, and unit operation time is the actual time spent on producing a unit. Allowance refers to additional time added for personal or unforeseen breaks.