PERT technique deals with the project of

Show Hint

PERT is used for projects with uncertain timelines where task durations are variable and follow a probabilistic distribution
Updated On: Dec 30, 2024
  • probabilistic nature
  • deterministic nature
  • non-repetitive nature
  • repetitive nature
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

The PERT Program Evaluation and Review Technique method is designed for projects with uncertain or probabilistic durations It considers the variability in task completion times and uses statistical methods to estimate project duration and probabilities
Was this answer helpful?