Step 1: Find the total work and individual rates.
Let the total work be LCM(8, 12) = 24 units.
Rate of P = \( \frac{24}{8} = 3 \) units/day.
Rate of Q = \( \frac{24}{12} = 2 \) units/day.
Step 2: Calculate the work done in one cycle (2 days).
The work is done on alternate days, starting with P.
Day 1 (P works): 3 units done.
Day 2 (Q works): 2 units done.
In one cycle of 2 days, a total of \( 3 + 2 = 5 \) units of work is completed.
Step 3: Find how many full cycles are needed.
Total work is 24 units.
Number of cycles = \( \lfloor \frac{24}{5} \rfloor = 4 \) full cycles.
Work completed in 4 cycles = \( 4 \times 5 = 20 \) units.
Time taken for 4 cycles = \( 4 \times 2 = 8 \) days.
Step 4: Calculate the remaining work and the time to complete it.
Remaining work = \( 24 - 20 = 4 \) units.
After 8 days, it is P's turn to work (on the 9th day).
P can do 3 units in one day. So, on the 9th day, P completes 3 units.
Work remaining after 9 days = \( 4 - 3 = 1 \) unit.
Time taken so far = 9 days.
Now it is Q's turn to work (on the 10th day). Q's rate is 2 units/day.
Time for Q to do the remaining 1 unit of work = \( \frac{\text{Remaining Work}}{\text{Q's Rate}} = \frac{1}{2} \) of a day.
Wait, let me recheck.
P:3, Q:2. Cycle=5 units in 2 days. Total=24.
4 cycles \textrightarrow 20 units in 8 days. Remaining = 4.
Day 9 (P's turn): P does 3 units. Remaining = 1. Time = 9 days.
Day 10 (Q's turn): Q needs to do 1 unit. Time = 1/2 day.
Total time = 9.5 days. This is option (B).
Let's re-read the question. P starts. P(8), Q(12).
Day 1: P (3)
Day 2: Q (2) \textrightarrow Total 5
...
Day 8: Q \textrightarrow Total 20.
Day 9: P (3) \textrightarrow Total 23.
Remaining work = 1 unit.
Day 10: Q's turn. Q's rate is 2 units/day. Time to do 1 unit = 1/2 day.
Total time = 9.5 days.
Let me check the other option \(9\frac{2}{3}\).
Remaining 1 unit. Q does it. Time = 1/2 day. Total 9.5
Where could \(9\frac{2}{3}\) come from? Maybe if P had to do the last bit.
Let's say after 9 days (23 units done), Q works. Remaining work is 1. Q's rate is 2. Time is 1/2.
Maybe I miscalculated the rates. P=1/8, Q=1/12. Work = 1.
2 days work = 1/8 + 1/12 = (3+2)/24 = 5/24.
In 8 days (4 cycles), work done = 4 (5/24) = 20/24.
Remaining = 4/24 = 1/6.
Day 9 (P's turn): P's rate is 1/8. \(1/8>1/6\) is false. P can complete his work.
Remaining after P works: \(1/6 - 1/8 = (4-3)/24 = 1/24\).
This means P works for the full 9th day. Work left is 1/24.
Day 10 (Q's turn): Q's rate is 1/12. Time to do 1/24 work = \( (1/24) / (1/12) = 1/2 \).
Total time = 9.5 days.
The answer seems to be consistently 9.5 days. Let's re-examine \(9\frac{2}{3}\).
This means after 9 days, 2/3 of a day is needed. Whose turn? Q's turn.
Work done by Q in 2/3 day = \( \frac{2}{3} \times \frac{1}{12} = \frac{1}{18} \).
The math does not support \(9\frac{2}{3}\). There must be an error in the provided options/answer. My calculation points to 9.5 days.