Question:

Match the following items of work in Group-I with their corresponding units of measurement in Group-II.


 

Show Hint

When working on construction projects, always be aware of the standard units of measurement for different types of work to avoid errors in calculations and estimates.
Updated On: Apr 15, 2025
  • P–1, Q–4, R–3, S–2
  • P–3, Q–1, R–4, S–5
  • P–5, Q–2, R–1, S–4
  • P–3, Q–4, R–1, S–2
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

Each type of work in construction has a specific unit of measurement, and we need to match each item with its appropriate unit.

Step 1: Honeycomb Brickwork is typically measured in Square Meters because the area of the brickwork surface is being calculated. Hence, P–3.

Step 2: Steel Reinforcement is measured in Kilograms, as the weight of steel reinforcement is a critical factor in construction, particularly for the calculation of material quantities. Hence, Q–4.

Step 3: Brick on Edge is typically counted by the Number of bricks, as each brick is individually considered in this type of work. Hence, R–1.

Step 4: Earthwork in Excavation is usually measured in Cubic Meters, as the volume of earth removed is the primary unit of measurement for excavation works. Hence, S–2.

Thus, the correct match is (D) P–3, Q–4, R–1, S–2.