Match the following items of work in Group-I with their corresponding units of measurement in Group-II.

A construction project consists of four activities. The duration, relationship, and cost parameters are given in the table. The indirect cost of the project is INR 5000 per week. If the project has to be completed by 12 weeks, the total project cost will be, INR _________ (Answer in integer)
Fish : Shoal :: Lion : _________
Select the correct option to complete the analogy.
The given figure is reflected about the horizontal dashed line and then rotated clockwise by 90° about an axis perpendicular to the plane of the figure.
Which one of the following options correctly shows the resultant figure?
Note: The figures shown are representative