Step 1: Span in years
Jan 1, 2006 Jan 1, 2010 spans 4 years (2006, 2007, 2008, 2009).
Step 2: Identify leap years
Among these, only 2008 is a leap year (divisible by 4, not by 100).
Step 3: Compute day shift
Each ordinary year shifts the weekday by +1; each leap year by +2.
Total shift $3\times 1 + 1\times 2 = 5$ days.
Step 4: Move 5 days ahead from Sunday
Sun Mon (a) Tue (b) Wed (c) Thu (d) \boxed{\text{Fri (5)}}.
\[
\boxed{\text{Friday (Option (c)}}
\]