In a bord and pillar panel, a square pillar of size 35 m \( \times \) 35 m (centre to centre) is extracted to form four equal square-shaped stooks as shown. The width of each gallery and crosscut is 5 m. The height of the working seam is 3 m. The reduction in safety factor after pillar splitting by using Bieniawski’s pillar strength formula, in %, is _______ (rounded off to 2 decimal places).
Bieniawski's pillar strength formula is given by \( S_p = S_1 \left( 0.64 + 0.36 \frac{w}{h} \right) \), where \( S_1 \) is the strength of a 0.9 m\(^3\) coal block, \( w \) is the pillar width, and \( h \) is the mining height.
In a bord and pillar panel, a square pillar of size 35 m \( \times \) 35 m (centre to centre) is extracted to form four equal square-shaped stooks as shown. The width of each gallery and crosscut is 5 m. The height of the working seam is 3 m. The reduction in safety factor after pillar splitting by using Bieniawski’s pillar strength formula, in %, is _______ (rounded off to 2 decimal places).

Bieniawski's pillar strength formula is given by \( S_p = S_1 \left( 0.64 + 0.36 \frac{w}{h} \right) \), where \( S_1 \) is the strength of a 0.9 m\(^3\) coal block, \( w \) is the pillar width, and \( h \) is the mining height.
In a Brazilian test, the front view of a homogeneous rock sample is shown in the figure. The failure initiates at the point, where the rock sample is subjected to stress. The failure initiates at the point marked as:

Reciprocal levelling is performed for points P and Q by placing the same levelling instrument at A and B. The observations of staff readings are tabulated as below. 
If the Reduced Level (RL) of P is 115.246 m, then the true RL of Q, in m, is _______ (rounded off to 3 decimal places)
The information of a mining project for a life of three years is given below:
Additional data: Applicable tax rate = 30%
Discount rate = 10%
Depreciation method: Straight line with zero salvage value
Data from a borehole log with collar elevation at 590 mRL are given below. Composite grade is calculated using cores of 5 m above and below the reference bench at 580 mRL. The composite grade, in %, is: