Question:

If P is the standard consistency of cement the amount of water used in conducting the initial setting time test on cement is.

Updated On: Mar 21, 2024
  • 0.65 P
  • 0.85 P
  • 0.6 P
  • 0.8 P
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

The correct option is(B): 0.85 P