Question:

If 40 boys can do a piece of work in 18 days working 6 hours per day, how many more boys are required to do the same work in 12 days working 4 hours per day?

Show Hint

Total work = workers × days × hours/day; keep total work constant while changing variables to find unknown.
Updated On: May 16, 2025
  • 50
  • 56
  • 40
  • 45
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

Calculate total work in boy-hours: \[ \text{Work} = \text{number of boys} \times \text{days} \times \text{hours/day} = 40 \times 18 \times 6 = 4320 \text{ boy-hours} \] Let $x$ be the number of additional boys needed, so total boys = $40 + x$. The new work schedule is 12 days, 4 hours/day, so: \[ (40 + x) \times 12 \times 4 = 4320 \] \[ (40 + x) \times 48 = 4320 \implies 40 + x = \frac{4320}{48} = 90 \] \[ x = 90 - 40 = 50 \]
Was this answer helpful?
0
0