Question:

If 1 man or 2 women can finish a job in 20 days, how many days will 3 men and women take to finish the same job?

Show Hint

To solve problems involving work and rates, find the combined rate of work by adding the individual rates of the workers.
Updated On: Oct 14, 2025
  • 3
  • 5
  • 6
  • 4
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

We are given that 1 man or 2 women can finish a job in 20 days. This implies the work done by 1 man in 1 day is \( \frac{1}{20} \), and the work done by 1 woman in 1 day is \( \frac{1}{40} \) (since 2 women together can finish the job in 20 days, so 1 woman will take 40 days). Now, for 3 men and \( x \) women working together, their combined work per day will be: \[ \text{Work per day} = 3 \times \frac{1}{20} + x \times \frac{1}{40} \] The total work done in 1 day by the group is equal to \( \frac{1}{4} \), so: \[ 3 \times \frac{1}{20} + x \times \frac{1}{40} = \frac{1}{4} \] Solving this equation: \[ \frac{3}{20} + \frac{x}{40} = \frac{1}{4} \] Multiplying through by 40 to eliminate the fractions: \[ 6 + x = 10 \] \[ x = 4 \] Thus, the number of women working is 4, and the total number of workers is 3 men and 4 women. The time required to complete the job will be: \[ \text{Time} = \frac{1}{\text{Work per day}} = \frac{1}{\frac{1}{4}} = 4 \text{ days} \] Thus, the answer is \( 4 \) days.
Was this answer helpful?
0
0