To determine the truthfulness of the given statements, we need to analyze them step-by-step.
Statement I:
"Ram and Shyam can finish a task by working together in 6 days. If Shyam can finish the task by working alone in 8 days, then Ram alone will take 24 days to finish it."
- The key to solving this is understanding the concept of work equivalence. If Shyam can complete the work alone in 8 days, we can say Shyam's work rate is \(\frac{1}{8}\) of the work per day.
- When Ram and Shyam work together, they complete the work in 6 days, which implies their combined work rate is \(\frac{1}{6}\) of the work per day.
- Let Ram's work rate be \(\frac{1}{R}\) work per day.
According to the given statements:
- \(\frac{1}{R} + \frac{1}{8} = \frac{1}{6}\)
Solving for \(\frac{1}{R}\):
- \(\frac{1}{R} = \frac{1}{6} - \frac{1}{8} = \frac{8-6}{48} = \frac{1}{24}\)
- This means Ram alone takes 24 days to finish the work, confirming that Statement I is true.
Statement II:
"If 6 persons working 8 hours a day earn 8,400 per week, then 9 persons working 6 hours a day will earn 9,450 per week."
- First, calculate the total hours worked by 6 persons in a week:
\(6 \times 8 \times 7 = 336\) hours - Given earnings are 8,400 for 336 hours, the hourly wage is \(\frac{8400}{336} = 25\) per hour
- Now, calculate the total weekly hours for 9 persons working 6 hours per day: \(9 \times 6 \times 7 = 378\) hours
- Therefore, the earnings for 378 hours at 25 per hour is: \(378 \times 25 = 9,450\)
- This confirms that Statement II is true.
Conclusion: Both Statement I and Statement II are true, confirming that the provided answer option "Both Statement I and Statement II are true" is correct.