Question:

For a given activity, the optimistic time, pessimistic time and most probable estimates are 5, 17, 8 days respectively. The expected time is

Updated On: Mar 21, 2024
  • 8 days
  • 9 days
  • 10 days
  • 15 days
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

The correct option is(B): 9 days