

To determine the MOST volatile activity, we need to evaluate the variance of each activity using the given optimistic, pessimistic, and most likely times. This is often done using the Program Evaluation and Review Technique (PERT) formula.
Pert Formula for Variance:
The variance of an activity in PERT is calculated as:
\(\text{Variance} = \left(\frac{\text{Pessimistic} - \text{Optimistic}}{6}\right)^2\)
Let's calculate the variance for each activity:
By comparing the variances, Activity G has the highest variance of \(\frac{25}{36}\), making it the MOST volatile activity.
Conclusion: The correct answer is \(G\).
To determine the most volatile activity, we need to assess the variability of each activity using the following formula for the standard deviation (SD) in the PERT (Program Evaluation and Review Technique) method: SD = (Pessimistic time - Optimistic time) / 6. This provides a measure of uncertainty or volatility in the time estimate for each activity.
| Activity | Optimistic Time (O) | Most Likely Time (M) | Pessimistic Time (P) |
|---|---|---|---|
| A | 3 | 6 | 15 |
| B | 3 | 4 | 18 |
| C | 3 | 4 | 8 |
| D | 4 | 5 | 10 |
| E | 3 | 5 | 12 |
| F | 3 | 4 | 14 |
| G | 3 | 9 | 27 |
| H | 2 | 4 | 8 |
| I | 6 | 9 | 18 |
By applying the formula:
The highest standard deviation is for Activity G with a value of 4. Therefore, Activity G is the most volatile for the chef.