Consider a Pelton wheel of 1 m diameter. The magnitude of relative velocity of water at the bucket inlet is the same as the magnitude of relative velocity of water at the bucket exit. The absolute speed of water at the bucket inlet is 125.66 m/s\(^{-1}\). For maximum power output from the Pelton wheel, the rpm of the Pelton wheel is (rounded off to 1 decimal place).
To calculate the rpm of the Pelton wheel for maximum power output, we need to consider the relationship between the velocity of water, the diameter of the Pelton wheel, and the rpm. Given: \[ D = 1 \ {m}, \quad V_1 = 125.66 \ {m/s} \] For maximum power output in a Pelton wheel, the bucket speed \( u \) is: \[ u = \frac{V_1}{2} = \frac{125.66}{2} = 62.83 \ {m/s} \] The linear speed \( u \) is related to rotational speed \( N \) by: \[ u = \frac{\pi D N}{60} \Rightarrow N = \frac{60u}{\pi D} \] Substituting the known values: \[ N = \frac{60 \cdot 62.83}{\pi \cdot 1} = \frac{3769.8}{\pi} \approx 1200.0 \ {rpm} \]
Correct Answer: 1200.0 rpm
A simply supported beam of length 1 m is subjected to a uniformly distributed bending moment of 1 N m per meter throughout the length as shown in the figure. The bending moment at the mid-point of the beam is __________ N m (rounded off to the nearest integer).

Cylindrical workpieces of diameter 60 mm and length 400 mm are machined on a lathe at a cutting speed of 25 m/min and a feed of 0.2 mm/rev. The Taylor’s tool life parameters \(C\) and \(n\) for this setup are 75 and 0.25, respectively. The tool changing time is 3 minutes. With a labor and overhead cost of ₹5 per minute, the tool changing cost per piece is ₹_________ (rounded off to 2 decimal places).
A company uses 3000 units of a part annually. The units are priced as given in the table below. It costs ₹150 to place an order. Carrying costs are 40 percent of the purchase price per unit on an annual basis. The minimum total annual cost is ₹ _________ (rounded off to 1 decimal place).

A project involves eight activities with the precedence relationship and duration as shown in the table below. The slack for the activity D is __________ hours (answer in integer).

Consider two identical tanks with a bottom hole of diameter \( d \). One tank is filled with water and the other tank is filled with engine oil. The height of the fluid column \( h \) is the same in both cases. The fluid exit velocity in the two tanks are \( V_1 \) and \( V_2 \). Neglecting all losses, which one of the following options is correct?
