Question:

Amar, Akbar and Anthony are working on a project. Working together Amar and Akbar can complete the project in 1 year, Akbar and Anthony can complete in 16 months, Anthony and Amar can complete in 2 years. If the person who is neither the fastest nor the slowest works alone, the time in months he will take to complete the project is

Updated On: Jul 23, 2024
Hide Solution
collegedunia
Verified By Collegedunia

Solution and Explanation

Let the total work be \(48\) units.
Let Amar do \(m\) work, Akbar do \(k\) work, and Anthony do \(n\) units of work in a month.
Amar and Akbar complete the project in \(12\) months.
Hence, in a month they do \(\frac {48}{12}=4\) units of work.
\(⇒m+k = 4\)   ……… (i)
Similarly,
\(k+n = 3\)       ……….. (ii)
and \(m+n = 2\)     ……… (iii)
On solving these equations,
\(m=\frac 32\)

\(k=\frac 52\)

\(n=\frac 12\)
Here, Amar works neither the fastest not the slowest and he does 1.5 units of work in a month.
Hence, to complete the work, time taken,
\(=\frac {48}{1.5}\)

\(= 32\) months

So, the answer is \(32\) months.

Was this answer helpful?
3
3

Top Questions on Mixture Problems

View More Questions

Questions Asked in CAT exam

View More Questions