Let the total work be \(48\) units.
Let Amar do \(m\) work, Akbar do \(k\) work, and Anthony do \(n\) units of work in a month.
Amar and Akbar complete the project in \(12\) months.
Hence, in a month they do \(\frac {48}{12}=4\) units of work.
\(⇒m+k = 4\) ……… (i)
Similarly,
\(k+n = 3\) ……….. (ii)
and \(m+n = 2\) ……… (iii)
On solving these equations,
\(m=\frac 32\)
\(k=\frac 52\)
\(n=\frac 12\)
Here, Amar works neither the fastest not the slowest and he does 1.5 units of work in a month.
Hence, to complete the work, time taken,
\(=\frac {48}{1.5}\)
\(= 32\) months
So, the answer is \(32\) months.