Let's break down this problem step-by-step:
1. Aman's Work Rate:
- Aman does 50% (1/2) of the job in 16 days.
- Aman does 100% (1) of the job in 16 * 2 = 32 days.
- Aman's work rate is 1/32 of the job per day.
2. Bhanu's Work Rate:
- Bhanu does 25% (1/4) of the job in 24 days.
- Bhanu does 100% (1) of the job in 24 * 4 = 96 days.
- Bhanu's work rate is 1/96 of the job per day.
3. Combined Work Rate:
- Their combined work rate is (1/32) + (1/96) per day.
- To add these fractions, find a common denominator (96):
- (3/96) + (1/96) = 4/96 = 1/24 of the job per day.
4. Time to Complete 1/4 of the Job:
- Let 'x' be the number of days they take to complete 1/4 of the job.
- Their combined work rate multiplied by the number of days should equal 1/4 of the job:
- (1/24) * x = 1/4
- x = (1/4) / (1/24)
- x = (1/4) * (24/1)
- x = 24/4
- x = 6 days
Therefore, they can do 1/4 of the job working together in 6 days.
The correct answer is Option.