Comprehension

Abdul has 8 factories, with different capacities, producing boutique kurtas. In the production process, he incurs raw material cost, selling cost (for packaging and transportation) and labour cost. These costs per kurta vary across factories. In all these factories, a worker takes 2 hours to produce a kurta. Pro t per kurta is calculated by deducting raw material cost, selling cost and labour cost from the selling price (Pro t = selling price - raw materials cost - selling cost - labour cost). Any other cost can be ignored. 

#Production Capacity
(No of Kurtas)
Selling Price / Kurta (₹)Profit / Kurta (₹)Selling Cost / Kurta (₹)Labour Cost / Hour (₹)
Factory 12500480077560450
Factory 21500530080045400
Factory 3800580090060550
Factory 41000550080068450
Factory 51500540060075600
Factory 61100600087565400
Factory 72500490050085350
Factory 82000530060070420
Question: 1

Which of the following options is in decreasing order of raw materials cost?

Show Hint

When “raw materials” isn’t given directly, back it out with the profit identity: \(\text{Profit}=\text{SP}-(\text{Raw}+\text{Selling Cost}+\text{Labour})\). Don’t forget to convert labour cost to a \emph{per-unit} value using the time per item.
Updated On: Aug 23, 2025
  • Factory 3, Factory 4, Factory 7, Factory 5
  • Factory 4, Factory 3, Factory 2, Factory 5
  • Factory 6, Factory 3, Factory 5, Factory 7
  • Factory 6, Factory 8, Factory 7, Factory 2
  • Factory 8, Factory 3, Factory 2, Factory 4
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

To determine the decreasing order of raw materials cost, we first need to calculate the raw material cost per kurta for each factory. The formula for raw material cost is given by:

Raw Material Cost per Kurta (RMC) = Selling Price - Profit - Selling Cost - Labour Cost

  • Factory 3:
    RMC = 5800 - 900 - 60 - (550*2) = 3740
  • Factory 4:
    RMC = 5500 - 800 - 68 - (450*2) = 3682
  • Factory 7:
    RMC = 4900 - 500 - 85 - (350*2) = 3615
  • Factory 5:
    RMC = 5400 - 600 - 75 - (600*2) = 3525
  • Factory 6:
    RMC = 6000 - 875 - 65 - (400*2) = 4260
  • Factory 8:
    RMC = 5300 - 600 - 70 - (420*2) = 3790
  • Factory 2:
    RMC = 5300 - 800 - 45 - (400*2) = 3655

Now, we sort the factories based on the raw material cost in decreasing order:

  • Factory 6: 4260
  • Factory 8: 3790
  • Factory 3: 3740
  • Factory 4: 3682
  • Factory 2: 3655
  • Factory 7: 3615
  • Factory 5: 3525

From the given options, the correct decreasing order of raw materials cost that matches is:

Factory 3, Factory 4, Factory 7, Factory 5

Was this answer helpful?
0
0
Question: 2

Which of the factories listed in the options below has the lowest sales margin (sales margin = profit per kurta divided by selling price per kurta)?

Show Hint

When comparing sales margins across multiple factories/products, always check the \(\frac{CP}{SP}\) ratio. The closer it is to 1, the smaller the margin, regardless of the absolute profit.
Updated On: Aug 23, 2025
  • Factory 2
  • Factory 4
  • Factory 5
  • Factory 6
  • Factory 7
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is

Solution and Explanation



1) Understanding the concept.
The sales margin is calculated as: \[ \text{Sales Margin} = \frac{\text{Profit per kurta}}{\text{Selling Price per kurta}}. \] Here, \(\text{Profit per kurta} = \text{Selling Price} - \text{Cost Price}\). Thus: \[ \text{Sales Margin} = \frac{\text{Selling Price} - \text{Cost Price}}{\text{Selling Price}} = 1 - \frac{\text{Cost Price}}{\text{Selling Price}}. \]

2) Implication.
The sales margin is lowest when the \(\frac{\text{Cost Price}}{\text{Selling Price}}\) ratio is highest. In other words, if the cost price is almost equal to the selling price, the margin is very low.


3) Application to given factories.
By analyzing the data (selling prices and costs of each factory given in the table of the set this question belongs to): - Factory 2 had a moderate difference between selling and cost.
- Factory 4 had a reasonable margin.
- Factory 5 and Factory 6 had visibly higher margins than Factory 7.
- Factory 7 had its cost price nearly equal to its selling price, making its margin the smallest.


4) Conclusion.
Hence, the lowest sales margin belongs to

Factory 7.
Was this answer helpful?
0
0
Question: 3

Abdul has received an order for 2{,}000 kurtas from a big retail chain. They will collect the finished pre-packaged kurtas directly from the factories, saving him the selling cost. To deliver this order, he can use multiple factories for production. Which of the following options will ensure maximum profit from this order?

Show Hint

When selling cost is removed, treat it as a pure \emph{cost minimization / contribution maximization} problem: sort factories by per-unit contribution and fill demand from the top contributors while respecting capacities.
Updated On: Aug 23, 2025
  • Factory 1
  • Factories 2 and 3
  • Factories 4 and 6
  • Factories 3, 6 and 4
  • Factory 1 or Factory 7 or Factory 8
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

Step 1: Objective after selling cost is waived.
Since the retailer picks up the goods, Abdul bears \emph{no selling cost}. Profit per kurta from factory $i$ becomes \[ \text{Contribution}_i=\text{Order price received}-\text{(production + packaging cost at }i\text{)}. \] Thus, to maximize profit for a fixed demand (2,000 units) with factory-wise capacities, allocate production in \emph{descending order of contribution per unit} until the demand is met.

Step 2: Rank factories by contribution and meet demand.
From the given DI table (from the set), the highest contributions are achieved by

Factory 3, then

Factory 6, followed by

Factory 4. Their combined capacity suffices to complete 2,000 kurtas; using any lower-contribution factory would reduce total profit.

Step 3: Eliminate alternatives.
\begin{itemize} \item

(A) Single factory either lacks capacity or has lower contribution than the top trio. \item

(B) and

(C) do not exhaust the best contributions and/or fall short on capacity at maximum margin. \item

(E) Proposes single lower-margin choices; suboptimal versus combining the top three. \end{itemize}

Final Answer: \[ \boxed{\text{(D) Factories 3, 6 and 4}} \]
Was this answer helpful?
0
0
Question: 4

Abdul has introduced a new technology in all his factories. As a result, a worker needs just $1.5$ hours to produce a kurta. If raw materials cost and selling cost remain the same, which factory (among the options) will now yield the \emph{highest profit per kurta?}

Show Hint

When some costs remain unchanged and only the time per unit changes, adjust profit by \(\Delta t \times\) (labour cost per hour). Ranking factories then reduces to comparing “old profit \(+\) 0.5 × labour/hr.”
Updated On: Aug 23, 2025
  • Factory 2
  • Factory 3
  • Factory 4
  • Factory 5
  • Factory 6
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

Step 1: What changes with the new technology?
Original labour time per kurta $=2$ hrs; new time $=1.5$ hrs.
Raw material and selling costs stay unchanged, and selling price is unchanged.
Hence the

only change in profit per kurta is the labour component: \[ \Delta(\text{profit per kurta}) \;=\; (2-1.5)\times(\text{labour cost per hour}) \;=\; 0.5 \times \text{(labour/hr)}. \] Therefore, \[ \text{New profit per kurta} \;=\; \text{Old profit per kurta} \;+\; 0.5 \times \text{(labour/hr)}. \]

Step 2: Compute the new profit for the listed factories (using the exhibit). \[ \begin{aligned} \text{F2:}&\quad 800 + 0.5\times 400 = 1000,
\text{F3:}&\quad 900 + 0.5\times 550 = 1175,
\text{F4:}&\quad 800 + 0.5\times 450 = 1025,
\text{F5:}&\quad 600 + 0.5\times 600 = 900,
\text{F6:}&\quad 875 + 0.5\times 300 = 1025. \end{aligned} \]

Step 3: Conclusion.
The maximum new profit per kurta is \(\mathbf{1175}\) at

Factory 3.

Final Answer: \[ \boxed{\text{B. Factory 3}} \]
Was this answer helpful?
0
0

Top Questions on Data Interpretation

View More Questions

Questions Asked in XAT exam

View More Questions