A project network with the sequence of five activities is shown.
A project network with the sequence of five activities
The crashing costs of activities are
ActivityABCDE
Duration (week) 56834
Crashing cost per week (lakh INR)4.02.52.03.04.0
If the project is crashed by one week, the increase in project cost, in lakh INR, is

Updated On: Jul 18, 2024
  • 2.0
  • 2.5
  • 3.0
  • 4.0
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

The correct option is (B): 2.5