A project network with the sequence of five activities is shown.
The crashing costs of activities are
Activity
A
B
C
D
E
Duration (week)
5
6
8
3
4
Crashing cost per week (lakh INR)
4.0
2.5
2.0
3.0
4.0
If the project is crashed by one week, the increase in project cost, in lakh INR, is
GATE MN - 2024
GATE MN
Updated On:
Jan 29, 2025
2.0
2.5
3.0
4.0
Hide Solution
Verified By Collegedunia
The Correct Option is
B
Solution and Explanation
The correct option is (B): 2.5
Download Solution in PDF
Was this answer helpful?
0
1
Top Questions on Network Analysis
What will be the stability for the following transfer function?
\( G(s) = \frac{50}{s(s+5)} \)
AP PGECET - 2025
Electronics and Communication Engineering
Network Analysis
View Solution
AP PGECET - 2025
Electronics and Communication Engineering
Network Analysis
View Solution
Find the values of $V_{Th}$ & $R_{Th}$ in the given circuit.
AP PGECET - 2025
Electronics and Communication Engineering
Network Analysis
View Solution
Which of the following is the Laplace equation?
AP PGECET - 2025
Electronics and Communication Engineering
Network Analysis
View Solution
A phase lag-lead network introduces in the output_______.
AP PGECET - 2025
Electronics and Communication Engineering
Network Analysis
View Solution
View More Questions
Questions Asked in GATE MN exam
In bord and pillar mining, the main load-bearing elements are:
GATE MN - 2026
Mine planning and its components
View Solution
The machine used for drilling blast holes in hard rock mines is:
GATE MN - 2026
Mine planning and its components
View Solution
Which one of the following is the most widely used method for coal extraction in surface mines?
GATE MN - 2026
Mine planning and its components
View Solution
Which gas is mainly responsible for explosions in coal mines?
GATE MN - 2026
Mine planning and its components
View Solution
The instrument commonly used for measuring horizontal and vertical angles in mines is:
GATE MN - 2026
Mine planning and its components
View Solution
View More Questions