A project network consists of the following activities
\[\begin{array}{|c|c|c|} \hline \textbf{Activity} & \textbf{Immediate Predecessors} & \textbf{Duration (days)} \\ \hline \text{A} & \text{--} & 3 \\ \hline \text{B} & \text{--} & 4 \\ \hline \text{C} & \text{A, B} & 5 \\ \hline \text{D} & \text{B} & 6 \\ \hline \text{E} & \text{D} & 7 \\ \hline \text{F} & \text{C, E} & 8 \\ \hline \text{G} & \text{D} & 9 \\ \hline \text{H} & \text{F, G} & X \\ \hline \end{array}\]
If the project completion time is 30 days, then the value of \( X \), in days, is \(\underline{\hspace{2cm}}\) (in integer).

Find the values of $V_{Th}$ & $R_{Th}$ in the given circuit.
Reciprocal levelling is performed for points P and Q by placing the same levelling instrument at A and B. The observations of staff readings are tabulated as below. 
If the Reduced Level (RL) of P is 115.246 m, then the true RL of Q, in m, is _______ (rounded off to 3 decimal places)
The information of a mining project for a life of three years is given below:
Additional data: Applicable tax rate = 30%
Discount rate = 10%
Depreciation method: Straight line with zero salvage value
Data from a borehole log with collar elevation at 590 mRL are given below. Composite grade is calculated using cores of 5 m above and below the reference bench at 580 mRL. The composite grade, in %, is: