Question:

A manufacturing unit produces two products P1 and P2. For each piece of P1 and P2, the table below provides quantities of materials M1, M2, and M3 required, and also the profit earned. The maximum quantity available per day for M1, M2 and M3 is also provided. The maximum possible profit per day is ₹ ________________.

Show Hint

For linear programming problems with two variables, check corner points formed by constraint intersections. The maximum profit always lies at a feasible corner.
Updated On: Dec 1, 2025
  • 5000
  • 4000
  • 3000
  • 6000
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

Let $x$ be the number of P1 units produced and $y$ be the number of P2 units produced. Material constraints are: \[ \text{M1: } 2x + 3y \le 70, \qquad \text{M2: } 2x + y \le 50, \qquad \text{M3: } 2y \le 40 \Rightarrow y \le 20. \] Profit function: \[ Z = 150x + 100y. \] Use the binding constraint $y = 20$ (since M3 is tight). Substitute in M1 and M2: \[ 2x + 3(20) \le 70 \Rightarrow 2x \le 10 \Rightarrow x \le 5, \] \[ 2x + 20 \le 50 \Rightarrow x \le 15. \] So the limiting value is $x = 5$. Profit: \[ Z = 150(5) + 100(20) = 750 + 2000 = 2750. \] But check if $y = 0$ gives higher profit (profit per M1 is better for P1): \[ 2x \le 70 \Rightarrow x = 35 \quad\text{but M2: } 2x \le 50 \Rightarrow x \le 25. \] So $x = 25, y = 0$. Profit: \[ Z = 150(25) = 3750. \] Now check the intersection of M1 and M2 constraints: Solve \[ 2x + 3y = 70, \qquad 2x + y = 50. \] Subtract: \[ 2y = 20 \Rightarrow y = 10, \] \[ 2x + 10 = 50 \Rightarrow x = 20. \] Profit: \[ Z = 150(20) + 100(10) = 3000 + 1000 = 4000. \] This is the maximum feasible profit. Final Answer: 4000
Was this answer helpful?
0
0

Questions Asked in GATE exam

View More Questions