>
Exams
>
Quantitative Aptitude
>
Time and Work
>
a contractor undertakes to build a wall in 50 days
Question:
A contractor undertakes to build a wall in 50 days. He employs 50 people for the same. However, after 25 days he finds that only 40\% of the work is complete. How many more men need to be employed to complete the work in time?
Show Hint
N/A
SNAP - 2012
SNAP
Updated On:
Sep 2, 2025
25
30
35
20
Hide Solution
Verified By Collegedunia
The Correct Option is
A
Solution and Explanation
N/A
Download Solution in PDF
Was this answer helpful?
0
0
Top Questions on Time and Work
A and B can complete a task in the ratio 3:2. If together they complete the task in 20 days, how long will A alone take?
CUET (UG) - 2025
General Aptitude
Time and Work
View Solution
A and B are employed to complete a work. When A worked at twice his normal efficiency and B worked at half his normal efficiency, the work was completed in 17 days. If A had worked at five times his normal efficiency and B worked at one-fourth of his normal efficiency, the work would have been completed in 10 days. If B works alone, how many days does he need to complete the work?
NMAT - 2025
Quantitative Aptitude
Time and Work
View Solution
A can draw 10 illustrations in 5 days. B is three times as productive in twice the amount of time (in comparison to A). How many illustrations can B draw in a day?
NPAT - 2025
Quantitative Aptitude
Time and Work
View Solution
A can complete a job in 12 days and B in 15 days. They work together for 5 days, and then A leaves. How many more days will B take to finish the remaining work?
CUET (UG) - 2025
General Aptitude
Time and Work
View Solution
If 5 workers can complete a job in 12 days, how long will 8 workers take to complete the same job (assuming all work at the same rate)?
CUET (UG) - 2025
General Aptitude
Time and Work
View Solution
View More Questions
Questions Asked in SNAP exam
Find the correct number that will complete the series:
14, 26, 36, 44, 50, ________, 56
SNAP - 2024
Number System
View Solution
Find the smallest number between 2000 and 3000 that is exactly divisible by 21, 24 and 28.
SNAP - 2024
Number System
View Solution
Select the combination of numbers so that letters arranged accordingly will form a meaningful word.
SNAP - 2024
Number System
View Solution
Find the missing letter/number
SNAP - 2024
Number System
View Solution
Find \(\sqrt{\,4^{6x^{2}}..... 25^{\,y/2}..... 9..... z^{4}\,}\).
SNAP - 2024
Number Systems
View Solution
View More Questions