Question:

A contract is to be completed in 50 days and 105 men were set to work, each working 8 hours a day. After 25 days, \(\frac 25th\) of the work is finished. How many additional men be employed so that the work may be completed on time, each man now working 9 hours a day?

Updated On: Jul 29, 2024
  • 34
  • 36
  • 35
  • 37
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

The correct option is (C) : 35.
Was this answer helpful?
0
0

Top Questions on Time and Work

View More Questions