Question:

A completes \( \frac{7}{10} \) of a work in 15 days and then he completes the remaining work with the help of B in 5 days. In how many days can A and B together complete the entire work?

Show Hint

When working with rates, combine the rates of individuals working together to find the total work rate, and then calculate the time needed to complete the task.
Updated On: Sep 24, 2025
  • 13 \( \frac{1}{3} \)
  • 15 \( \frac{3}{4} \)
  • 14 \( \frac{1}{4} \)
  • 16 \( \frac{2}{3} \)
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation


Step 1: Work Done by A.
A completes \( \frac{7}{10} \) of the work in 15 days. The work done by A in 1 day is: \[ \text{Work rate of A} = \frac{7}{10} \div 15 = \frac{7}{150} \]

Step 2: Work Done by A and B Together.
The remaining work is \( 1 - \frac{7}{10} = \frac{3}{10} \). A and B together complete this work in 5 days, so their combined work rate is: \[ \text{Work rate of A and B} = \frac{3}{10} \div 5 = \frac{3}{50} \] Since A's work rate is \( \frac{7}{150} \), the work rate of B is: \[ \text{Work rate of B} = \frac{3}{50} - \frac{7}{150} = \frac{9}{150} - \frac{7}{150} = \frac{2}{150} = \frac{1}{75} \]

Step 3: Time for A and B Together to Complete the Work.
The combined work rate of A and B is: \[ \text{Work rate of A and B together} = \frac{7}{150} + \frac{1}{75} = \frac{7}{150} + \frac{2}{150} = \frac{9}{150} = \frac{3}{50} \] The total time to complete the entire work is: \[ \text{Time} = \frac{1}{\text{Work rate of A and B together}} = \frac{50}{3} = 13 \frac{1}{3} \, \text{days} \]

Final Answer: \[ \boxed{13 \frac{1}{3} \, \text{days}} \]

Was this answer helpful?
0
0