Question:

A company has a job to prepare certain number of cans and there are three machines A, B, and C for this job. A can complete the job in 3 days, B can complete the job in 4 days, and C can complete the job in 6 days. How many days will the company take to complete the job if all the machines are used simultaneously?

Show Hint

When multiple entities work together, their combined rate of work is the sum of their individual rates. The total time taken is the reciprocal of the combined rate.
Updated On: Aug 4, 2025
  • 4 days
  • \(\frac{4}{3}\) days
  • 3 days
  • 12 days
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

Let the total work be represented by \( W \). The rates of work for each machine are:
- A can complete the work in 3 days, so its rate of work is \( \frac{W}{3} \).
- B can complete the work in 4 days, so its rate of work is \( \frac{W}{4} \).
- C can complete the work in 6 days, so its rate of work is \( \frac{W}{6} \).
When all three machines work together, their combined rate of work is the sum of their individual rates:
\[ \text{Combined rate of work} = \frac{W}{3} + \frac{W}{4} + \frac{W}{6}. \] To simplify this, we first find the least common denominator of 3, 4, and 6, which is 12:
\[ \frac{W}{3} = \frac{4W}{12}, \quad \frac{W}{4} = \frac{3W}{12}, \quad \frac{W}{6} = \frac{2W}{12}. \] Thus, the combined rate of work is:
\[ \frac{4W}{12} + \frac{3W}{12} + \frac{2W}{12} = \frac{9W}{12} = \frac{3W}{4}. \] This means the machines together complete \(\frac{3W}{4}\) of the work in one day.
Therefore, the time taken to complete the entire work is the reciprocal of the combined rate:
\[ \text{Time taken} = \frac{1}{\frac{3}{4}} = \frac{4}{3} \text{ days}. \] Thus, the correct answer is \(\frac{4}{3}\) days.
Was this answer helpful?
0
0