Question:

A can do a piece of work in x days and B can do the work in 3x days. To finish the work together, they take 12 days. What is the value of x?

Show Hint

For combined work problems, add individual work rates and equate to the combined rate.
Updated On: Jun 6, 2025
  • 8
  • 10
  • 12
  • 16
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is D

Solution and Explanation

Step 1: Work rates
- A’s rate = \(\frac{1}{x}\) work per day
- B’s rate = \(\frac{1}{3x}\) work per day
Step 2: Combined rate
\[ \frac{1}{x} + \frac{1}{3x} = \frac{1}{12} \] \[ \frac{3 + 1}{3x} = \frac{1}{12} \] \[ \frac{4}{3x} = \frac{1}{12} \] Step 3: Solve for \(x\)
Cross multiply:
\[ 4 \times 12 = 3x \] \[ 48 = 3x \] \[ x = 16 \] Thus, Option (D) 16 is correct.
Was this answer helpful?
0
0