Question:

A can do a piece of work in 25 days, B can do it in 20 days. They started the work together but A left 5 days before the completion of the work. The work has finished in?

Updated On: Oct 4, 2024
  • \(13 \frac {1}{3}\) days
  • \(15 \frac {3}{7}\) days
  • \(11 \frac {4}{9}\) days
  • \(9 \frac {3}{8}\) days
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

The correct option is (A): \(13 \frac {1}{3}\) days.
Was this answer helpful?
0
0

Top Questions on Time and Work

View More Questions