Question:

A can do a piece of work in 25 days and B in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?

Updated On: Aug 20, 2025
  • 17 days
  • 11 days
  • 10 days
  • 15 days
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

To solve this problem, we need to calculate the combined work of A and B for 5 days, then determine how many more days B will need to finish the remaining work alone.
First, calculate the work done by each in one day:
  • A can complete the task in 25 days, so A's one day work = 1/25.
  • B can complete the task in 20 days, so B's one day work = 1/20.
Next, calculate their combined work for one day:
Combined work of A and B in one day = 1/25 + 1/20
= (4 + 5) / 100
= 9/100.
Now, calculate the work done by both in 5 days:
Work done in 5 days = 5 * 9/100 = 45/100 = 9/20.
The remaining work = Total work - Work done in 5 days
Remaining work = 1 - 9/20 = 11/20.
Finally, find out how many more days B, working alone, will take to complete the remaining work:
Since B's one day work = 1/20, the time taken by B to complete 11/20 work = (11/20) / (1/20) = 11.
Therefore, B will take 11 days to finish the remaining work.
Was this answer helpful?
0
0