Question:

A can do a job in 9.8 days and B can do it in 14 days. They work together for 3.5 days, and A goes away. In how many days will B finish the remaining work?

Updated On: Oct 23, 2024
  • 3.6 days
  • 5.5 days
  • 6.3 days
  • 7.2 days
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

The correct answer is (B);5.5 days