A, B, and C together complete the job in 10 days.
\(\therefore\) Their combined efficiency is \(( \frac{1}{10} )\) of the job per day.
\(\therefore\) A+B+C worked for the first 3 days and completed \(( \frac{37}{100} )\) of the job.
After the first 3 days, the remaining work is \(( 1 - \frac{37}{100} = \frac{63}{100} )\).
A and B complete this remaining work in ( 10 - 3 = 7 ) days.
Therefore, their combined efficiency is \(( \frac{63}{100} \div 7 = \frac{9}{100} )\) of the job per day.
It is given that,
the work done by A in 5 days is equal to the work done by B in 4 days, \([ 5 \times \text{Work Rate of A} = 4 \times \text{Work Rate of B} ] [ \frac{\text{Work Rate of A}}{\text{Work Rate of B}} = \frac{4}{5} ]\)
Now,
Let the efficiency of A be ( 4x ) and the work rate of B be ( 5x ).
\(\therefore\) \(( 4x + 5x = \frac{9}{100} \Rightarrow 9x = \frac{9}{100} \Rightarrow x = \frac{1}{100} )\).
efficiency of A is \(( 4x = 4 \times \frac{1}{100} = \frac{4}{100} = \frac{1}{25} )\).
efficiency of B is \(( 5x = 5 \times \frac{1}{100} = \frac{5}{100} = \frac{1}{20} )\).
Hence, B is the fastest worker and can complete the entire job in 20 days.