Question:

'A' and 'B' complete a work in 12 days, 'B' and 'C' in 8 days and 'C' and 'A' in 16 days. 'A' left after working for 3 days. In how many days more will 'B' and 'C' finish the remaining work?

Show Hint

When given pairwise work rates, add them to find the total for all three, then subtract to get individual rates.
Updated On: Aug 14, 2025
  • 6 \(\frac{1}{6}\) days
  • 2.7 days
  • 3.4 days
  • 4.3 days
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

Step 1: Write work rates for each pair.
From the question:
A + B = \(\frac{1}{12}\) work/day
B + C = \(\frac{1}{8}\) work/day
C + A = \(\frac{1}{16}\) work/day
Step 2: Find total of A + B + C.
Adding all three equations:
(A + B) + (B + C) + (C + A) = \(\frac{1}{12} + \frac{1}{8} + \frac{1}{16}\)
2(A + B + C) = \(\frac{4 + 6 + 3}{48} = \frac{13}{48}\)
So A + B + C = \(\frac{13}{96}\) work/day
Step 3: Find each individual rate.
From A + B = \(\frac{1}{12}\), we have: A + B = \(\frac{8}{96}\).
Subtract from A + B + C: C = \(\frac{13}{96} - \frac{8}{96} = \frac{5}{96}\) work/day.
From B + C = \(\frac{1}{8} = \frac{12}{96}\), we get B = \(\frac{12}{96} - \frac{5}{96} = \frac{7}{96}\) work/day.
From C + A = \(\frac{1}{16} = \frac{6}{96}\), we get A = \(\frac{6}{96} - \frac{5}{96} = \frac{1}{96}\) work/day.
Step 4: Work done by A, B, and C in first 3 days.
Daily combined rate = A + B + C = \(\frac{13}{96}\).
Work done in 3 days = \(3 \times \frac{13}{96} = \frac{39}{96}\) of the total work.
Step 5: Remaining work.
Remaining work = \(1 - \frac{39}{96} = \frac{57}{96}\).
Step 6: B and C’s combined rate.
B + C = \(\frac{12}{96}\) work/day.
Step 7: Time required for remaining work.
Time = \(\frac{\frac{57}{96}}{\frac{12}{96}} = \frac{57}{12} = 4.75 \ \text{days}\).
So the exact answer is 4 \(\frac{3}{4}\) days, which is approximately 4.75 days.
Was this answer helpful?
0
0

Questions Asked in CLAT exam

View More Questions