Question:

A and B can separately do a piece of work in 20 and 15 days, respectively. They worked together for 6 days, after which B was replaced by C. If the work was finished in the next 4 days, then the number of days in which C alone could do the work will be

Updated On: Sep 26, 2024
  • 60 days
  • 40 days
  • 35 days
  • 30 days
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

Work done by A in one day \(=\frac{1}{20}\) and work done by B in one day \(=\frac{1}{15}\)

Work done by both A and B in one day \(=\frac{1}{20}+\frac{1}{15}=\frac{7}{60}\)

Work done by A and B in 6 days \(=\frac{7}{60}\) × 6 \(=\frac{7}{10}\)

Remaining Work \(=1-\frac{7}{10}=\frac{3}{10}\)

Now, Time taken by A and B to complete the work in next 4 days is given by

⇒ (Remaining work / (A + C)'s effeciency) = Remaining time to complete the work.

⇒ \(\frac{1}{20}+\frac{1}{C}=4 days\)

⇒ \(\frac{3}{10}=4(\frac{1}{20}+\frac{1}{C})\)

⇒ \(\frac{3}{10}=\frac{4}{20}+\frac{4}{C}\) ⇒ \(\frac{4}{C}=\frac{3}{10}-\frac{1}{5}\)

⇒ \(\frac{1}{C}=\frac{1}{40} \) (or) C = 40 days

Hence, option B is the correct answer.The correct option is (B): 40 days
Was this answer helpful?
0
0

Top Questions on Time and Work

View More Questions