Question:

A and B can finish a work in 10 days and 15 days respectively. They together work on it for 5 days and then the rest of the work is finished by C in 2 days. They get INR 450 for finishing this work. What should be the shares of A, B, and C respectively?

Show Hint

When dividing the total payment based on the work done, divide the total work based on the rates of work of each individual and allocate the payment accordingly.
Updated On: Aug 22, 2025
  • A = INR 180, B = INR 120, C = INR 150
  • A = INR 225, B = INR 120, C = INR 105
  • A = INR 225, B = INR 150, C = INR 75
  • None of these
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

Let the total work be \( W \).
A’s rate of work = \( \frac{1}{10} \) work/day,
B’s rate of work = \( \frac{1}{15} \) work/day.
Together A and B work for 5 days, so the work done by A and B is:
\[ \text{Work done by A and B in 5 days} = 5 \times \left( \frac{1}{10} + \frac{1}{15} \right) \] \[ = 5 \times \left( \frac{3}{30} + \frac{2}{30} \right) = 5 \times \frac{5}{30} = \frac{25}{30} = \frac{5}{6} \] So, the remaining work is:
\[ \text{Remaining work} = 1 - \frac{5}{6} = \frac{1}{6} \] C finishes the remaining work in 2 days, so C’s rate of work is:
\[ \text{C’s rate of work} = \frac{1}{6} \div 2 = \frac{1}{12} \text{ work/day} \] Now, we divide the INR 450 according to their work contributions:
- A’s contribution in 5 days = \( 5 \times \frac{1}{10} = \frac{5}{10} = \frac{1}{2} \),
- B’s contribution in 5 days = \( 5 \times \frac{1}{15} = \frac{5}{15} = \frac{1}{3} \),
- C’s contribution in 2 days = \( 2 \times \frac{1}{12} = \frac{2}{12} = \frac{1}{6} \).
Total work = \( 1 \).
Therefore, the share of each person:
- A’s share = \( \frac{1}{2} \times 450 = 225 \),
- B’s share = \( \frac{1}{3} \times 450 = 150 \),
- C’s share = \( \frac{1}{6} \times 450 = 75 \). Answer: A gets INR 225, B gets INR 150, and C gets INR 75.
Was this answer helpful?
0
0