Let the total work be \( W \).
A’s rate of work = \( \frac{1}{10} \) work/day,
B’s rate of work = \( \frac{1}{15} \) work/day.
Together A and B work for 5 days, so the work done by A and B is:
\[
\text{Work done by A and B in 5 days} = 5 \times \left( \frac{1}{10} + \frac{1}{15} \right)
\]
\[
= 5 \times \left( \frac{3}{30} + \frac{2}{30} \right) = 5 \times \frac{5}{30} = \frac{25}{30} = \frac{5}{6}
\]
So, the remaining work is:
\[
\text{Remaining work} = 1 - \frac{5}{6} = \frac{1}{6}
\]
C finishes the remaining work in 2 days, so C’s rate of work is:
\[
\text{C’s rate of work} = \frac{1}{6} \div 2 = \frac{1}{12} \text{ work/day}
\]
Now, we divide the INR 450 according to their work contributions:
- A’s contribution in 5 days = \( 5 \times \frac{1}{10} = \frac{5}{10} = \frac{1}{2} \),
- B’s contribution in 5 days = \( 5 \times \frac{1}{15} = \frac{5}{15} = \frac{1}{3} \),
- C’s contribution in 2 days = \( 2 \times \frac{1}{12} = \frac{2}{12} = \frac{1}{6} \).
Total work = \( 1 \).
Therefore, the share of each person:
- A’s share = \( \frac{1}{2} \times 450 = 225 \),
- B’s share = \( \frac{1}{3} \times 450 = 150 \),
- C’s share = \( \frac{1}{6} \times 450 = 75 \).
Answer: A gets INR 225, B gets INR 150, and C gets INR 75.