To find out after how many days A left the work, we first need to determine the work rate for A and B:
1/21 of the work per day.1/24 of the work per day.Let x be the number of days A worked before leaving. During these x days, both A and B work together:
The work done by A in x days = x/21.
The work done by B in x days = x/24.
Total work done by both A and B in x days = x/21 + x/24.
After A leaves, B completes the remaining work in 9 days. So, the work B does in these 9 days = 9/24 = 3/8.
The total work that needs to be done is 1 (since it is one complete piece of work). Therefore, we have:
x/21 + x/24 + 3/8 = 1
Now, solve for x:
First find the common denominator for the terms 21 and 24: the LCM is 168. The equation becomes:
(8x + 7x)/168 + 3/8 = 1
15x/168 + 3/8 = 1
Subtract 3/8 from both sides:
15x/168 = 1 - 3/8
15x/168 = 5/8
Now, solve for x:
15x = 168 * (5/8)
15x = 105
x = 105/15
x = 7
Therefore, A left the work after 7 days.