Time and cost over-runs have been a major problem affecting the implementation of Central Sector Projects. The trend of time over-runs and cost over-runs are given in the graphs below. Answer these questions based on these graphs.
Question: 1
The highest number of delayed projects during the given period was in the year
From the Given Graph, we can see that Number of delayed projects in year 1991 = 189 Number of delayed projects in year 1994 = 210 Number of delayed projects in year 1997 = 239 Number of delayed projects in year 1996 = 234
The correct option is (C)
Was this answer helpful?
0
0
Question: 2
The highest incidents of cost over-run during the given period has been in the year
From the Given Graph, we can see that Cost over-run in year 1991 = 61.6% Cost over-run in year 1994 = 57.5% Cost over-run in year 1997 = 45% Option A removes the possibility of Option D
The correct option is (A)
Was this answer helpful?
0
0
Question: 3
The number of delayed projects have been the same in the years
From the Given Graph, we can see that Number of delayed projects in year 1990 = 194 Number of delayed projects in year 1992 = 194 Number of delayed projects in year 1989 = 174 Number of delayed projects in year 2001 = 174 Thus option C removes the possibility of Option D
The correct option is (C)
Was this answer helpful?
0
0
Question: 4
The percentage cost over-runs have been the same in the years 2000 and 2001. It implies that