Question:

The total primary consolidation settlement (Sc) of a building constructed on a 10 m thick saturated clay layer is estimated to be 50 mm. After 300 days of the construction of the building, primary consolidation settlement was reported as 10 mm. The additional time (in days) required to achieve 50% of Sc will be _____ (rounded off to the nearest integer).

Updated On: Jul 17, 2024
Hide Solution
collegedunia
Verified By Collegedunia

Correct Answer: 1550

Solution and Explanation

The answer is: 1550 or 1600 (approx.)