Question:

The roof convergence data for 30 days at a monitoring station in a coal mine gallery is given.
DayConvergence reading (mm) 
00
54.7
1011.3
1619.6
2228.8
3034.8
The management decides on a Trigger Action Response Plan (TARP) if the following two premises occur simultaneously.
Premise 1: Rate of convergence exceeds 1.5 mm/day between two consecutive measurements. 
Premise 2: Rate of cumulative increase in convergence exceeds 1.0 mm/day. 
Identify the day on which TARP is enforced in that gallery. 

Updated On: Jul 18, 2024
  • 10
  • 16
  • 22
  • 30
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is C

Solution and Explanation

The correct option is (C): 22