A dummy activity is a fictitious activity used in project scheduling (PERT or CPM) to indicate dependency relationships between real activities.
It is not assigned any time or resources, but it is used to show that a specific activity cannot start until another is completed.
Dummy activities are used to complete the network and establish the correct sequence of tasks, even if there is no actual work involved in the activity.