Question:

The artificial activity which indicates that an activity following it cannot be started unless the preceding activity is complete, is known as

Show Hint

Dummy activities help establish the order of dependencies in project scheduling, without affecting the overall project duration.
Updated On: May 22, 2025
  • free float
  • dummy activity
  • slack activity
  • negative activity
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

  • A dummy activity is a fictitious activity used in project scheduling (PERT or CPM) to indicate dependency relationships between real activities.
  • It is not assigned any time or resources, but it is used to show that a specific activity cannot start until another is completed.
  • Dummy activities are used to complete the network and establish the correct sequence of tasks, even if there is no actual work involved in the activity.