Question:

Raman can do a piece of work in 16 days, Satish in 8 days, while Ashok can do it in 32 days. All started together but Satish left after 2 days. Raman left 3 days before the completion of the work. How long did it take to complete the entire work?

Show Hint

In work problems where people leave at different times, always assume total time as a variable and form a single work-equation using individual working durations.
Updated On: Jan 25, 2026
  • 8 days
  • 10 days
  • 12 days
  • 14 days
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is B

Solution and Explanation

Step 1: Write individual one-day work rates.
Raman can complete the work in 16 days, so his one-day work is \( \frac{1}{16} \).
Satish can complete the work in 8 days, so his one-day work is \( \frac{1}{8} \).
Ashok can complete the work in 32 days, so his one-day work is \( \frac{1}{32} \).
Step 2: Work done by all three in the first 2 days.
Combined one-day work of all three is:
\[ \frac{1}{16} + \frac{1}{8} + \frac{1}{32} \]
\[ = \frac{2 + 4 + 1}{32} = \frac{7}{32} \]
Work done in 2 days is:
\[ 2 \times \frac{7}{32} = \frac{14}{32} = \frac{7}{16} \]
Step 3: Work remaining after 2 days.
\[ 1 - \frac{7}{16} = \frac{9}{16} \]
Step 4: Raman leaves 3 days before completion.
Let total time taken to complete the work be \( x \) days.
Then Raman worked for \( (x - 3) \) days.
Satish worked only for 2 days.
Ashok worked for all \( x \) days.
Step 5: Total work equation.
\[ \frac{x-3}{16} + \frac{2}{8} + \frac{x}{32} = 1 \]
Step 6: Simplify the equation.
\[ \frac{x-3}{16} + \frac{1}{4} + \frac{x}{32} = 1 \]
Multiply entire equation by 32 to clear denominators.
\[ 2(x-3) + 8 + x = 32 \]
Step 7: Solve the equation.
\[ 2x - 6 + 8 + x = 32 \]
\[ 3x + 2 = 32 \]
\[ 3x = 30 \]
\[ x = 10 \]
Step 8: Final conclusion.
Hence, the total time taken to complete the work is 10 days.
Was this answer helpful?
0
0

Top Questions on Time and Work

View More Questions