Question:

Prime cost consists of —

Show Hint

Prime Cost = Direct Costs only
Updated On: Feb 21, 2026
  • Direct material + Direct labour + Direct expenses
  • Direct material + Factory overhead
  • Direct labour + Administrative overhead
  • All indirect costs
Hide Solution
collegedunia
Verified By Collegedunia

The Correct Option is A

Solution and Explanation

Prime cost includes all direct costs of production. \[ \text{Prime Cost} = \text{Direct Material} + \text{Direct Labour} + \text{Direct Expenses} \] Final Answer: \[ \boxed{(A)} \]