- Option (A): A dummy activity does not consume time or resources. It is used to represent logical relationships between activities in network diagrams.
- Option (B): The PERT method is indeed most suitable for projects where there is high uncertainty in the durations of activities, as it incorporates probabilistic estimates for activity durations.
- Option (C): A Gantt chart is a bar chart used for planning and scheduling but does not specifically identify the critical path. The critical path method (CPM) is used for identifying the critical path.
- Option (D): Free float refers to the amount of time an activity can be delayed without affecting the start of a following activity.
Thus, the correct answers are (B) and (D).