Step 1: Understanding critical path.
In the Critical Path Method (CPM), the critical path is the longest path in the project schedule. It determines the minimum time required to complete the project.
Step 2: Activities with zero float.
The critical path consists of activities that have zero total float, meaning there is no room for delay. Any delay in these activities will directly result in a delay of the entire project.