To determine the correct answer, let's analyze each given option based on the work rates of Anuj, Bharat, Chetan, and Dhiraj.
- Anuj completes the job in 1 day. His work rate is \(\frac{1}{1} = 1\text{ job/day}\).
- Bharat takes twice the time of Anuj, so he takes 2 days to complete the job. His work rate is \(\frac{1}{2} \text{ job/day}\).
- Chetan takes twice the time of Bharat, so he takes 4 days. His work rate is \(\frac{1}{4} \text{ job/day}\).
- Dhiraj takes twice the time of Chetan, so he takes 8 days. His work rate is \(\frac{1}{8} \text{ job/day}\).
Next, let's evaluate the given statements:
- (A) Chetan and Dhiraj will take 8/3 days to complete the work.
- The combined work rate of Chetan and Dhiraj is \(\frac{1}{4} + \frac{1}{8} = \frac{3}{8} \text{ jobs/day}\).
- The time taken to complete one job at this rate is \(\frac{1}{\frac{3}{8}} = \frac{8}{3} \text{ days}\).
- This statement is correct.
- (B) The second fastest pair to complete the work is Anuj and Dhiraj.
- Pairs considered: Anuj & Bharat, Anuj & Chetan, Anuj & Dhiraj, Bharat & Chetan, Bharat & Dhiraj, Chetan & Dhiraj.
- The pair Anuj & Bharat has the highest rate after Anuj & Chetan, thus faster than Anuj & Dhiraj.
- This statement is incorrect.
- (C) The second slowest pair to complete the work is Bharat and Dhiraj.
- The combined work rate for Bharat & Dhiraj is \(\frac{1}{2} + \frac{1}{8} = \frac{5}{8} \text{ jobs/day}\).
- Calculate work rate for other pairs and compare:
- Anuj & Dhiraj: \(\frac{1}{1} + \frac{1}{8} = \frac{9}{8} \text{ jobs/day}\)
- Chetan & Dhiraj: \(\frac{3}{8} \text{ jobs/day}\)
- Bharat & Dhiraj is indeed the second slowest pair after Chetan & Dhiraj.
- This statement is correct.
- (D) Bharat and Dhiraj will take 4/3 days to complete the work.
- The combined work rate of Bharat and Dhiraj is \(\frac{5}{8}\) jobs/day.
- The time taken to complete one job is \(\frac{1}{\frac{5}{8}} = \frac{8}{5} \text{ days}\).
- This statement is incorrect.
Based on our analysis, the correct answer is: (A) and (C) only.